Heavy structural fabrication
Frames, platforms, supports, stairways and equipment structures, fabricated for erection and access.
Heavy structural fabrication, tanks, reactors, chimneys, ducting, painting and insulation, produced at our G.I.D.C. Ankleshwar workshop and delivered to site.
Fabrication · dispatch · site erection
Fabrication is only half the job. The other half is the route: can it be lifted, shipped, walked into the plant and erected without rework?
We plan the split, the lifting points, the transport envelope and the site joints before cutting steel. The workshop at Plot 262, G.I.D.C. Ankleshwar, is equipped for the work and close enough to the Bharuch chemical belt to respond when a plant needs something quickly.
From a single support frame to a complete tank or stack, the work is built to drawing, inspected and dispatched with the records the site needs.
Frames, platforms, supports, stairways and equipment structures, fabricated for erection and access.
Process equipment and vessels for chemical and industrial plants, built to the client's drawing and specification.
Industrial chimney fabrication and erection in the height and diameter the plant needs, with quality checks at each stage.
Ducting, supports and thermal insulation for process and utility systems, fabricated and installed as one scope.
Surface preparation, industrial painting and finishing that protects the steel and meets the site's specification.
Lifting, alignment, bolting and welding on site, using our own crews and the lifting plan the job requires.
A selection of the fabrication and erection work that comes through the Ankleshwar workshop.






A selected equipment list. The workshop is backed by the lifting, welding, cutting and rolling capacity needed to finish and dispatch the work.
| Equipment | Capacity | Quantity |
|---|---|---|
| Hydraulic crane | 15 MT | 1 |
| Hydraulic crane | 12 MT | 1 |
| Hydra crane | 11 MT | 1 |
| Plate rolling machine | 16 mm | 1 |
| Welding rectifier | 3 phase | 29 |
| Welding transformer | 3 / 2 phase | 17 |
| Plasma cutting machine | 3 phase | 1 |
| MIG welding machine | CO₂ operated | 1 |
| Pedestal drilling machine | 32 mm | 3 |
| Magnetic drill machine | 32 mm | 5 |
| Derrick | 30 m | 1 set |
| Derrick | 40 m | 1 set |
| Electric winch | 20 MT / 15 MT | 2 |
| Gas cutting set | — | 35 |
| Chain pulley block | 10 / 5 / 3 / 2 MT | 19 |
Other tools and tackles are held at the store and mobilised to site as the work requires.
Material, dimensions, fit-up, weld quality and finish are checked as the work moves through the shop. The point is not a certificate at the end; it is that the piece arrives at site ready to install.
Under our ISO 9001:2015 quality system, inspection and testing are documented, and the handover pack follows the equipment to site.